Hyundai E&C may ask KT to foot growing bill for remodeling project

image

A rendered image of the KT Gwanghwamun West Building after renovation / Courtesy of Heerim Architects & Planners

Hyundai E&C could seek additional payment from KT for the remodeling of the Gwanghwamun Building owned by the telecommunication company, which is also embroiled in a conflict with Ssangyong E&C over construction costs for its Pangyo Office Building, according to industry officials, Friday.

The construction unit of Hyundai Motor Group has been remodeling the KT Gwanghwamun West Building since September 2021, planning to complete the construction by March 2025.

Both companies are initially said to have agreed to the construction cost of 180 billion won ($136 million), but the soaring material and labor costs over the past two years led the construction firm to spend an additional 30 billion won on the project.

A Hyundai E&C official admitted that it is true that the company and KT have differing views about the construction costs.

“The size of our loss from the construction is not small,” the official said.

Unlike Ssangyong E&C that staged a protest on Tuesday in front of the Pangyo KT Office Building in Seongnam, Gyeonggi Province, to ask for the payment of an additional 17.1 billion won, Hyundai E&C has yet to demand additional costs be paid by KT.

There is a speculation that their recent partnership has made it difficult for Hyundai E&C to make such a request to KT.

During President Yoon Suk Yeol’s state visit to Saudi Arabia last month, both companies signed a memorandum of understanding to build a data center in the Middle Eastern country, by taking advantage of KT’s capability in digital transformation and Hyundai E&C’s expertise in smart construction.

However, the Hyundai E&C official denied that the relationship has any effect on the Gwangwhamun Building project.

Citing the contract that rules out price adjustments in case of inflation or deflation, KT had once rejected Ssangyong E&C’s request. But KT held internal discussions after the construction firm’s protest. Ssangyong E&C threatened to stage another protest in front of the KT Gwanghwamun Building in central Seoul, if the telecommunications firm rejects negotiations.

Hyundai E&C expects KT would pay the additional amount, once an agreement is reached with Ssangyong E&C.

Last year, mid-sized construction company, Hanshin E&C, and another major builder, Lotte E&C, also reportedly clashed with KT over construction costs.

As a growing number of construction firms have clashed with their clients amid the worsening business environment, the government advised builders and clients in August to be clear about how they will adjust construction costs in case of price fluctuations.