Daewoo E&C seeks gov't mediation in dispute over Czech nuclear project
Summary
Daewoo Engineering & Construction asked the Ministry of Trade, Industry and Resources on Monday to mediate its dispute with Korea Hydro & Nuclear Power over the Dukovany nuclear project in the Czech Republic. The request followed KHNP’s notice Friday that it had ended contract negotiations after rejecting Daewoo E&C’s revised proposal. Daewoo E&C said the contractor should not bear additional costs and risks for building the APR1000 model in Europe for the first time. KHNP plans a new tender in July 2027, with construction scheduled to begin four months later.
Key Facts
- The Dukovany project is valued at about 25 trillion won, or $17.5 billion.
- The project involves two Korean-designed APR1000 reactors, each with a capacity of 1,000 megawatts.
- Daewoo E&C submitted its revised proposal on Thursday and said it did not adequately account for rising construction costs.
- Daewoo E&C leads the construction consortium for the project.
- KHNP said it plans to launch a new tender in July 2027.

Aerial view of Dukovany nuclear power plant in the Czech Republic / Yonhap
Daewoo Engineering & Construction (E&C) said Monday it has asked the government to mediate a dispute with Korea's state-run nuclear power operator over a major nuclear reactor project in the Czech Republic.
The company, which leads a construction consortium for the project, made the request to the Ministry of Trade, Industry and Resources after receiving formal notice Friday that Korea Hydro & Nuclear Power (KHNP) Co. had ended contract negotiations.
"We have requested the ministry's mediation to resume contract negotiations and normalize the project as soon as possible," Daewoo E&C said in a statement.
The Dukovany project, valued at about 25 trillion won ($17.5 billion), involves the construction of two 1,000-megawatt APR1000 nuclear reactors, a Korean-designed model, in the Czech Republic.
Daewoo E&C said KHNP unilaterally ended the negotiations after rejecting its revised proposal submitted Thursday, citing the company's failure to adequately reflect rising construction costs.
The builder argued it was unreasonable to require a construction contractor, which is not responsible for reactor design, to bear additional costs and risks associated with building the APR1000 model in Europe for the first time.
KHNP said earlier it plans to launch a new tender to select a construction contractor in July 2027, with construction scheduled to begin four months later.